RFP 1-09-C100: Retrofit Aircraft Ground Power Units, Dulles Airport

|
PROJECT OVERVIEW
|
|
RFP Issue Date: June 19, 2009
Deadline for Proposals: 1:00 PM (Eastern), July 23, 2009
Pre-Proposal Conference: 10:00 AM (Eastern), July 7, 2009 at Conference Room D, Second Floor, 45045 Aviation Drive, Dulles Airport
Question Submission: The deadline for submitting questions has passed.
No further questions will be accepted.
Estimated Dollar Value: $100,000 - $200,000
Project Duration: 120 days from Notice to Proceed
Bond Requirements: 100% Payment, 100% Performance
Fee for Plans: $50.00 for printed documents; free download
Project Summary:
The Contractor shall provide all labor, materials, equipment and supevision necessary to retrofit two new 180Kva, 400Hz aircraft ground power units onto Jet Bridges at Washington Dulles International Airport.
LDBE Requirement:
None
Amendments Issued:
One, July 20, 2009 - The due date for proposals remains unchanged.
CLICK HERE to download Amendment Documents
Last Updated July 20, 2009