RFP 1-08-C223: Interior Metal Surface Painting, National Airport
|
|
|
|
PROJECT OVERVIEW
|
|
|
|
|
|
| RFP Issue Date: | July 30, 2008 | ||||||
| Deadline for Proposals: | 2:00 PM (Eastern), September 2, 2008 | ||||||
| Pre-Proposal Conference: | 10:00 AM (Eastern), August 6, 2008 at the MA-120 Conference Room, East Building, Second Floor, National Airport | ||||||
| Question Submission: | The deadline for submitting questions has passed. No further questions will be accepted. |
||||||
| Estimated Dollar Value: | $25,000 - $100,000 | ||||||
| Project Duration: | 180 days from Notice to Proceed | ||||||
| Bond Requirements: | 100% Paymemt and Performance Bonds | ||||||
| Fee for Plans: | $50.00 for printed documents; free download | ||||||
| Project Summary: | |||||||
| The Contractor shall furnish all necessary labor, materials, tools, equipment and supervision to paint interior structural steel beams and columns, interior and exterior guard rails and posts, metal doors and frames, and interior information display supports in Terminal B/C at Ronald Reagan Washington National Airport. | |||||||
| LDBE Requirement: | |||||||
| This RFP has a 100% Local Disadvantaged Business Enterprise (LDBE) participation requirement and a 100% Voluntary MBE/WBE goal. Firms located within a 100-mile radius and whose 3 year average gross receipts, including all affiliates, do not exceed the size standard(s) below are eligible for consideration. For more LDBE/MBE/WBE information, including other LDBE size standards, contact the Equal Opportunity Programs Department at 703-417-8625. | |||||||
| LDBE Size Standards: | |||||||
|
|||||||
| Amendments Issued: | |||||||
| One August 12, 2008 - The due date for proposals is entended from August 30, 2008 to September 2, 2008. CLICK HERE to download Amendment Documents |
|||||||
|
Last Updated August 15, 2008
|
|||||||